Pune Metro: First aluminium bodied coach to arrive in August 2021; Here’s how it looks

by salil123
Pune Metro - First aluminium bodied coach to arrive in August 2021; Here’s how it looks

Pune: The first aluminium bodied coaches to be used in Pune Metro will arrive in the month of August this year, which is just seven months away. The production of these coaches is likely to start in April 2021 and the first coach for Pune Metro is scheduled to be dispatched by August 15.

The model of coach for Pune Metro was unveiled on January 9 (Saturday) by Durga Shanker Mishra, Secretary, Ministry of Housing and Urban Affairs of the central government. Mishra visited the Titagarh Firema manufacturing facility setup for producing these first aluminium bodied metro coaches in India at the Kolkata Plant.

Pune Metro coach model unveiled

Pune Metro coach model unveiledAfter unveiling the model, Mishra took to his twitter account and updated the revised schedule for production and dispatch of the coaches for Pune Metro.

Mishra said, “Privileged to unveil model of coach for Pune Metro at Titagarh Firema HQ in Kolkata today. This is the first lightweight aluminium bodied coach which is fuel efficient and has additional safety and convenience features. Its design was finalised few months back and now model is ready.”

“First train set from Titagarh’s Italian Plant will get dispatched in May 2021 and from Kolkata Plant by August 15, 2021. Thanks Titagarh for adhering to delivery schedule despite challenges of Covid-19 in both places where its plants are located,” he added.

Pune Metro - First aluminium bodied coach to arrive in August 2021

Pune Metro – First aluminium bodied coach to arrive in August 2021

Mishra said, “Production in the factory is likely to start in April 2021 and the first coach for Pune is scheduled to be dispatched by August 15, 2021. The plant is being developed as an integrated plant with many key components such as bogies, propulsion etc to be ultimately produced in-house.”

“Titagarh plans to substitute imported components of rolling stocks with locally manufactured or outsourced parts and move swiftly towards 100 per cent Indian components within 3 years & then target global market. Impressive to see use of high level technology, ioT, AI & ML in manufacturing,” he said in one of his tweet.

“It is going to be paperless production line with high quality assurance. Was happy to see enthusiasm of young but highly experienced team. High motivation and high commitment to Atma Nirbhar Bharat will yield results! Best wishes Team Titagarh!,” he concluded.

Pune Metro trial run PCMC to Phugewadi January 3 2021

Pune Metro trial run PCMC to Phugewadi January 3 2021

The Maharashtra Metro Rail Corporation Limited (MahaMetro) on January 3 successfully completed the trial run of Pune Metro Rail Project on the six-kilometre stretch between Pimpri-Chinchwad Municipal Corporation (PCMC) and Phugewadi on the Metro Line 1 of PCMC to Swargate. This trial run was conducted one year after the first trial run on one-kilometre stretch between PCMC to Sant Tukaram Nagar was conducted on January 10, 2020.

So far, 45 per cent of the total work of the Pune Metro project has been completed. First the unseasonal rains in October to December 2019 had slowed down the metro project work. It resumed in January 2020, but again got affected in March 2020 when the nationwide lockdown was imposed to contain the spread of coronavirus. Overcoming all these odds, the MahaMetro has managed to cover up the lost time and complete 45 per cent of the work.

 